CEVA Logistics moves mining equipment to Chile

Copper mining company, Codelco, specified CEVA Logistics to transport nine enormous conveyor belts to northern Chile.

Each conveyor belt was approx. 2.06 x 4.2m and weighed a total of 58.8 tonnes.

Codelco is reported to have the largest known copper reserves and is also one of the largest producers of molybdenum in the world, in addition to being a major producer of rhenium, of which Chile is the largest producer worldwide.

CEVA’s scope was to receive the conveyor belts directly discharged from the vessel onto low bed trucks in the port of Las Losas and to transport them to an intermediate site in Antofagasta.

The belts’ sizes and dimensions required special transport permits which had to be adjusted, as well as equipment and personnel on a daily base, due to constant shifts in the vessel’s unloading program caused by strike and climate impacts in Port of Las Losas.

CEVA, despite the logistical challenges of rotating staff and equipment during the two weeks of the operation, managed to maintain the availability of all its resources – complying with accreditations, Covid-19 protocols and Health, Safety and Environment (HSE) requirements.

All nine low bed trailers were positioned on time for direct reception from the vessel and transported immediately to the destination, avoiding detention of overtime charges in the stand by period at the port. The belt’s installation at the job site was delayed, hence the on time delivery was imperative for the customer, in order not to affect production.

Codelco congratulated CEVA Logistics for the successful delivery of these critical components on time.

“This action increasingly demonstrates the strengthening of the Industrial Projects and Energy Services (IP&ES) service in the Latin America region,” said CEVA Logistics.

 